Reference project

Connecting the Dagály swimming complex to district heating

Connection of the Dagály swimming complex on Népfürdő utca to the district heating system.

Connection of the Dagály swimming complex on Népfürdő utca to the district heating system.

Scope of supply:

The new directly buried, pre-insulated hot water trunk main supplies the district heating pipelines of the existing Dagály baths and of the new swimming complex built by MNV Zrt. for the FINA World Championships. Our scope covered the removal and reinstatement of surfaces, earthworks, utility diversions, and the laying and commissioning of the district heating pipelines in line with the requirements of Főtáv Zrt.

Performance data:

Max. temperature: 140 ℃

Pressure rating: PN 25

Pipe size: DN 250/400; DN 200/355

Execution: July–October 2016