Reference project

Pécs power plant — 35 MWe straw-fired biomass unit

Basic, permit and detailed design, construction and commissioning of the complete straw-fired unit under an EPC contract.

Basic, permit and detailed design, construction and commissioning of the complete straw-fired unit under an EPC contract

Scope of supply (excluding the boiler):

Civil and architectural works, bale conveying system, 100 bar main steam system, feedwater system, BoP, medium and low voltage, control systems

Key data:

Output: 35 MWe Boiler: vibrating-grate, straw-fired Steam output: 137.2 t/h Steam parameters: 100 bar, 540ºC

Client: Dalkia/Pannonhő Execution: 2010–2013

Request a quote

Planning an energy project?

Send us the scope or the drawings — we will review them and agree the next step with you: design, construction or full EPC.